Construction Optimization in Arch Dams by Changing the Arrangement of Contraction Joints: a Proposal Based on Numerical Simulations

Título
Construction Optimization in Arch Dams by Changing the Arrangement of Contraction Joints: a Proposal Based on Numerical Simulations
Tipo
Artigo em Livro de Atas de Conferência Internacional
Ano
2021
Autores
José Conceição
(Autor)
FEUP
Miguel Azenha
(Autor)
Outra
A pessoa não pertence à instituição. A pessoa não pertence à instituição. A pessoa não pertence à instituição. Sem AUTHENTICUS Sem ORCID
Manuel Miranda
(Autor)
FEUP
Ver página pessoal Sem permissões para visualizar e-mail institucional Pesquisar Publicações do Participante Sem AUTHENTICUS Sem ORCID
Outras Informações
Resumo (PT):
Abstract (EN): In arch dams, significant volumetric deformations occur during construction – as a result of the heat released by cement hydration and the low thermal conductivity of the concrete –, which, if restrained, can lead to the occurrence of high tensile stresses. Consequently, arch dams are built through individual cantilever blocks, separated by contraction joints. This implies that, in each block, the concreting volumes decrease from the foundation to the crest, due to the reduction of the cantilever thickness, which diminishes the efficiency of the construction equipment installed on site for the first stages of the arch dam construction. This problem has been overcome in the past by interrupting some contraction joints at about 2/3 of the arch dam height, thus allowing to increase the concrete volume to be placed at each lift from then on, such as performed in Las Portas dam. Despite the benefits of this construction strategy, it is still not a current practice, due to the lack of numerical results that prove its efficiency. So, the present article aims to evaluate the possibility of modifying the arrangement of the contraction joints in order to reduce the construction time of arch dams. Using thermo-mechanical analyses, it is shown that the mentioned alternative arrangement of the contraction joints leads to a risk of concrete cracking identical to that obtained with the traditional arrangement normally adopted, which allows significant economic benefits, namely the reduction of the costs and time of construction.
Idioma: Inglês
Tipo (Avaliação Docente): Científica
Documentos
Não foi encontrado nenhum documento associado à publicação com acesso permitido.
Publicações Relacionadas

Dos mesmos autores

Numerical Study on Arch Dams Under the Construction and Operation Scenarios (2019)
Resumo de Comunicação em Conferência Internacional
Rui Faria; José Conceição; Miguel Azenha; Manuel Miranda
Recomendar Página Voltar ao Topo
Copyright 1996-2025 © Centro de Desporto da Universidade do Porto I Termos e Condições I Acessibilidade I Índice A-Z
Página gerada em: 2025-10-13 às 20:40:36 | Política de Privacidade | Política de Proteção de Dados Pessoais | Denúncias | Livro Amarelo Eletrónico