Assessment of the 2014 structural collapse of Batalha dos Guararapes viaduct, Brazil

Title
Assessment of the 2014 structural collapse of Batalha dos Guararapes viaduct, Brazil
Type
Article in International Scientific Journal
Year
2020
Authors
Real Pereira, SSR
(Author)
Other
The person does not belong to the institution. The person does not belong to the institution. The person does not belong to the institution. Without AUTHENTICUS Without ORCID
Carvalho, H
(Author)
Other
The person does not belong to the institution. The person does not belong to the institution. The person does not belong to the institution. Without AUTHENTICUS Without ORCID
Verga Mendes, VRV
(Author)
Other
The person does not belong to the institution. The person does not belong to the institution. The person does not belong to the institution. Without AUTHENTICUS Without ORCID
Journal
Vol. 172
Pages: 150-157
ISSN: 2043-9903
Publisher: ICE Publishing Ltd.
Indexing
Other information
Authenticus ID: P-00S-HE7
Abstract (EN): The urban viaduct Olimpio Mourao Filho in Belo Horizonte, Brazil, also known as Batalha dos Guararapes viaduct, partly collapsed while under construction in July 2014, killing two people. The 375?m structure consists of seven box-section spans that were concreted on-site and prestressed with post-tensioned cables. A week after the end of the central part shoring was removed, a central column and two adjacent spans collapsed onto the road below, killing two people. No additional loads had been applied from the beginning of the shoring removal until the collapse. This paper describes the viaduct project and analyses the reasons that led to the collapse. The collapsed column was supported by ten 0.8?m dia. piles. The failure occurred abruptly and was caused by insufficient longitudinal reinforcement of the pile cap block. At the time of the collapse, the column load was fully transferred to the two central piles, driving them 7.5?m into the ground and leading to the viaduct collapse.
Language: English
Type (Professor's evaluation): Scientific
No. of pages: 8
Documents
We could not find any documents associated to the publication.
Related Publications

Of the same journal

Editorial on reliability and safety of structures and infrastructures (2020)
Another Publication in an International Scientific Journal
Correia, JAFO; Pedro Aires Montenegro; Zhu, SP
Editorial (2018)
Another Publication in an International Scientific Journal
Correia, JAFO; Abilio M P De Jesus; Rui Calçada
Influence of reinforcement type on the flexural behaviour of reinforced concrete beams (2020)
Article in International Scientific Journal
Stronski, P; Blazejewski, W; Socha, T; Denisiewicz, A; Kula, K; Lesiuk, G; Correia, JAFO
Recommend this page Top
Copyright 1996-2025 © Faculdade de Direito da Universidade do Porto  I Terms and Conditions  I Acessibility  I Index A-Z
Page created on: 2025-09-12 at 13:01:21 | Privacy Policy | Personal Data Protection Policy | Whistleblowing | Electronic Yellow Book